This page is dedicated to updates on Fairgrounds improvement efforts including, but not limited to, planning, public engagement, design, upgrades and construction on the property. Check back often for the latest news on Fair Park, the speedway, new facility planning, MLS stadium, and mixed-use development.

Week in Review: May 6-10

May 13, 2019

Installation of the building envelope and canopy at Expo 1 continues. Steel erection for Shed 1 steel started this week and will continue into the next one...

Week in Review: April 29-May 3

May 6, 2019

The site grading contractor continued to haul off excess soil material and bring the hardscaped areas to grade...

Week in Review: April 22-26

April 29, 2019

The vapor barrier and wire mesh for Shed 2 were installed in preparation for concrete. Grading was completed for Fair Park, Phase II...